Permitting Action Modification History

Cancelled
It has been determined that this project should be analyzed under an EA and does not require an EIS. The EIS action is being cancelled, as a result of the determination to proceed with an EA., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 08-11-2026 08-11-2026 No
Scoping (Agency Action) 09-10-2026 09-10-2026 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-13-2027 08-13-2027 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-30-2028 06-30-2028 No
Issuance of Lead Agency Record of Decision (Agency Action) 08-14-2028 08-14-2028 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 08-11-2026 08-11-2026 No
Scoping (Agency Action) 09-10-2026 09-10-2026 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-13-2027 08-13-2027 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-30-2028 06-30-2028 No
Issuance of Lead Agency Record of Decision (Agency Action) 08-14-2028 08-14-2028 No