Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-31-2024 01-31-2024 Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 01-31-2024 01-31-2024 Yes
Section 106 consultation concluded (Agency Action) 02-27-2026 02-27-2026 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-31-2024 01-31-2024 Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 01-31-2024 01-31-2024 Yes
Section 106 consultation concluded (Agency Action) 02-27-2026 02-27-2026 No