Permitting Action Modification History
Modifications on 09/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 08-19-2023 | 08-19-2023 | --- | Yes |
| Submittal of complete initial Plan of Operations (Applicant Action) | 12-01-2023 | 12-01-2023 | --- | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-15-2023 | 12-15-2023 | --- | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 08-21-2026 | 08-21-2026 | --- | Yes |
| Approval of final Plan of Operations (Agency Action) | 09-07-2026 | 09-02-2026 | --- | Yes |
Modifications on 08/21/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 08-19-2023 | 08-19-2023 | --- | Yes |
| Submittal of complete initial Plan of Operations (Applicant Action) | 12-01-2023 | 12-01-2023 | --- | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-15-2023 | 12-15-2023 | --- | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 08-21-2026 | 08-21-2026 | --- | Yes |
| Approval of final Plan of Operations (Agency Action) | 09-07-2026 | 09-07-2026 | --- | No |
Modifications on 10/02/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 08-19-2023 | 08-19-2023 | --- | Yes |
| Submittal of complete initial Plan of Operations (Applicant Action) | 12-01-2023 | 12-01-2023 | --- | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-15-2023 | 12-15-2023 | --- | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 08-21-2026 | 08-21-2026 | --- | No |
| Approval of final Plan of Operations (Agency Action) | 09-07-2026 | 09-07-2026 | --- | No |