Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 12-05-2025 12-05-2025 --- Yes
Submittal of complete initial Plan of Operations (Applicant Action) 09-01-2026 09-01-2026 --- No
Acceptance of complete initial Plan of Operations (Agency Action) 03-05-2026 09-30-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 01-17-2028 01-17-2029 --- No
Approval of final Plan of Operations (Agency Action) 01-31-2028 01-31-2029 --- No
Planned
On December 15, 2026, Laramide Resources, Ltd. requested a schedule delay of six to twelve months to allow better alignment between the state and federal permitting processes. The revised schedule moves the final decision date by one calendar year.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 12-05-2025 12-05-2025 --- Yes
Submittal of complete initial Plan of Operations (Applicant Action) 09-01-2026 09-01-2026 --- No
Acceptance of complete initial Plan of Operations (Agency Action) 03-05-2026 09-30-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 01-17-2028 01-17-2029 --- No
Approval of final Plan of Operations (Agency Action) 01-31-2028 01-31-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 12-05-2025 12-05-2025 --- Yes
Acceptance of complete initial Plan of Operations (Agency Action) 03-05-2026 03-05-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 01-17-2028 01-17-2028 --- No
Approval of final Plan of Operations (Agency Action) 01-31-2028 01-31-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Submittal of draft initial Plan of Operations (Applicant Action) 12-05-2025 12-05-2025 --- No
Acceptance of complete initial Plan of Operations (Agency Action) 03-05-2026 03-05-2026 --- No
Submittal of final Plan of Operations and financial assurance (Applicant Action) 01-17-2028 01-17-2028 --- No
Approval of final Plan of Operations (Agency Action) 01-31-2028 01-31-2028 --- No