Permitting Action Modification History
Modifications on 10/16/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 10-15-2026 | 10-15-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-16-2026 | 11-16-2026 | No |
| ESA Consultation Concludes (Agency Action) | 03-31-2027 | 03-31-2027 | No |
Modifications on 06/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 10-15-2026 | 10-15-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-16-2026 | 11-16-2026 | No |
| ESA Consultation Concludes (Agency Action) | 03-31-2027 | 03-31-2027 | No |