Permitting Action Modification History
Modifications on 03/23/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 09-23-2014 | 09-23-2014 | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-05-2014 | 12-05-2014 | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 02-07-2026 | 05-08-2026 | No |
| Approval of final Plan of Operations (Agency Action) | 02-15-2026 | 05-15-2026 | No |
Modifications on 12/18/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 09-23-2014 | 09-23-2014 | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-05-2014 | 12-05-2014 | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 02-07-2026 | 05-08-2026 | No |
| Approval of final Plan of Operations (Agency Action) | 02-15-2026 | 05-15-2026 | No |
Modifications on 11/12/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 09-23-2014 | 09-23-2014 | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 12-05-2014 | 12-05-2014 | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 02-07-2026 | 02-07-2026 | No |
| Approval of final Plan of Operations (Agency Action) | 02-15-2026 | 02-15-2026 | No |