Permitting Action Modification History
Modifications on 02/19/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-23-2025 | 01-23-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-23-2025 | 01-28-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 01-14-2026 | 02-13-2026 | Yes |
Modifications on 02/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-23-2025 | 01-23-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-23-2025 | 01-28-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 01-14-2026 | 06-07-2026 | No |
Modifications on 02/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-23-2025 | 01-23-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-23-2025 | 01-28-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 01-14-2026 | 06-07-2026 | No |
Modifications on 09/25/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-23-2025 | 09-23-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-23-2025 | 10-23-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-14-2026 | 01-14-2026 | No |