Permitting Action Modification History

Complete
Section 106 completed 4/16/2026, basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-12-2025 08-12-2025 Yes
Section 106 consultation concluded (Agency Action) 01-14-2026 04-16-2026 Yes
In Progress
internal organization process changes for concurrences , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-12-2025 08-12-2025 Yes
Section 106 consultation concluded (Agency Action) 01-14-2026 04-24-2026 No
In Progress
Internal agency factors , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-12-2025 08-12-2025 Yes
Section 106 consultation concluded (Agency Action) 01-14-2026 03-27-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-12-2025 08-12-2025 Yes
Section 106 consultation concluded (Agency Action) 01-14-2026 01-14-2026 No