Permitting Action Modification History

Complete
Early completion of the prior milestone enabled early completion of the final milestone.  Also, the completed ESA consultation resulted in the issuance of an LOC -- the consultation was completed informally (whereas the original milestone reflected a formal consultation). The Action outcome was issuance of a Letter of Concurrence (LOC). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2026 04-01-2026 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 04-23-2026 04-23-2026 --- Yes
ESA Consultation Concludes (Agency Action) 10-14-2026 06-23-2026 --- Yes
In Progress
ESA consultation initiated early on 4/23/26. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2026 04-01-2026 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 04-23-2026 --- Yes
ESA Consultation Concludes (Agency Action) 10-14-2026 09-04-2026 --- No
Planned
milestone completed, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2026 04-01-2026 --- Yes
NOAA Requests Additional Information (Agency Action) 05-01-2026 05-01-2026 --- No
Lead Agency Responds to Additional Information Request (Agency Action) 05-15-2026 05-15-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No
Planned
NMFS provided a date of 4/2/26 for the first ESA and EFH milestones, but it was changed when populating the Dashboard and published as 4/1/26.  The revision corrected this error.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2026 04-02-2026 --- No
NOAA Requests Additional Information (Agency Action) 05-01-2026 05-01-2026 --- No
Lead Agency Responds to Additional Information Request (Agency Action) 05-15-2026 05-15-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2026 04-01-2026 --- No
NOAA Requests Additional Information (Agency Action) 05-01-2026 05-01-2026 --- No
Lead Agency Responds to Additional Information Request (Agency Action) 05-15-2026 05-15-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No