Permitting Action Modification History

Complete
USFWS determined informal consultation. Informal consultation completed early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-01-2026 04-22-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 05-18-2026 05-18-2026 --- Yes
ESA Consultation Concludes (Agency Action) 10-14-2026 05-20-2026 --- Yes
In Progress
Ahead of schedule., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-01-2026 04-22-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 05-18-2026 --- Yes
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-01-2026 04-22-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No
Planned
milestone completed early, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-01-2026 04-22-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-01-2026 05-01-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 06-01-2026 06-01-2026 --- No
ESA Consultation Concludes (Agency Action) 10-14-2026 10-14-2026 --- No