USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Milestone was completed ahead of target date, due to internal agency efforts., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-16-2026 --- Yes
Section 106 consultation concluded (Agency Action) 09-23-2026 09-10-2026 --- Yes
In Progress
Consultation initiated early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-16-2026 --- Yes
Section 106 consultation concluded (Agency Action) 09-23-2026 09-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-23-2026 --- No
Section 106 consultation concluded (Agency Action) 09-23-2026 09-23-2026 --- No