Permitting Action Modification History

In Progress
Milestone complete early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-12-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 02-17-2026 --- Yes
Publication of Public Notice (Agency Action) 03-02-2026 02-17-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No
Planned
Updated milestone because project sponsor submitted application earlier than projected. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-12-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 02-17-2026 --- No
Publication of Public Notice (Agency Action) 03-02-2026 03-02-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-15-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 02-17-2026 --- No
Publication of Public Notice (Agency Action) 03-02-2026 03-02-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No