Permitting Action Modification History

Complete
The Corps initiated Section 106 consultation with the Florida SHPO and three Tribal THPOs on March 2, 2026, 21 days ahead of the scheduled milestone date.  The Florida SHPO provided a letter concurring with the ‘no effect’ determination on April 1, 2026.  The three Tribal THPOs did not reply, and the Corps presumed concurrence on July 16, 2026.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-02-2026 --- Yes
Section 106 consultation concluded (Agency Action) 09-23-2026 07-16-2026 --- Yes
In Progress
Completed this milestone ahead of original target. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-02-2026 --- Yes
Section 106 consultation concluded (Agency Action) 09-23-2026 09-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-23-2026 03-23-2026 --- No
Section 106 consultation concluded (Agency Action) 09-23-2026 09-23-2026 --- No