USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
Milestones completed earlier than target date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-12-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 01-07-2026 --- Yes
Publication of Public Notice (Agency Action) 03-02-2026 01-09-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No
Planned
Updated milestone because project sponsor submitted application earlier than projected. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-12-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 02-17-2026 --- No
Publication of Public Notice (Agency Action) 03-02-2026 03-02-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 12-15-2025 12-15-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 02-17-2026 02-17-2026 --- No
Publication of Public Notice (Agency Action) 03-02-2026 03-02-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 03-02-2027 03-02-2027 --- No