Permitting Action Modification History
Modifications on 05/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 12-09-2026 | 04-28-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 04-29-2026 | 04-29-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 05-24-2027 | 05-06-2026 | Yes |
Modifications on 05/07/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 12-09-2026 | 04-28-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 05-24-2027 | 05-06-2026 | Yes |
Modifications on 04/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 12-09-2026 | 04-28-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 05-24-2027 | 05-24-2027 | No |
Modifications on 09/17/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 12-09-2026 | 12-09-2026 | No |
| ESA Consultation Concludes (Agency Action) | 05-24-2027 | 05-24-2027 | No |