USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-09-2026 --- Yes
Final decision/agency action (Agency Action) 04-03-2026 05-01-2026 --- Yes
In Progress
A Section 106 Tribal Consultation letter was received from the Alabama-Coushatta Tribe on March 4, 2026, requesting additional documentation, consideration, and avoidance measures for a potential cultural landscape. The time necessary to accommodate that request and provide an updated report for a final 30-day review has exceeded the currently scheduled completion date of the final decision document (FANEC). This milestone date change is therefore extending out the FANEC date by an additional two weeks. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-09-2026 --- Yes
Final decision/agency action (Agency Action) 04-03-2026 05-01-2026 --- No
In Progress
Section 106 Consultation conclusion had to be extended to accommodate completion of a preliminary review cycle by Tribal Nations. The Categorical Exclusion document cannot be executed until after the close of Section 106 Consultation. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-09-2026 --- Yes
Final decision/agency action (Agency Action) 04-03-2026 04-17-2026 --- No
In Progress
After review there are no longer any deficiencies and the APD/SUPO has been accepted as of 1/9/2026, ahead of 1/14/26 milestone date. Complete CE application and NEPA can now begin. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-09-2026 --- Yes
Final decision/agency action (Agency Action) 04-03-2026 04-03-2026 --- No
Planned
Just to follow up on what was discussed today:   Currently, Sponsor submits package on December 15 (or earlier, if possible). If no deficiencies on the package (BLM and USFS), accept on December 22. If deficient, issue letters of deficiency on December 22. If resubmittal is needed, Sponsor to submit revisions by January 7. If resubmittal is needed, Final determination by January 14 (assuming no additional deficiencies) .   The dashboard milestones for the 3 actions (Special Use Permit, Surface Use Plan [USFS], and Surface Use Plan [BLM]) will be changed to Jan 14. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-14-2026 --- No
Final decision/agency action (Agency Action) 04-03-2026 04-03-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-25-2025 06-25-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 12-22-2025 --- No
Final decision/agency action (Agency Action) 04-03-2026 04-03-2026 --- No