Permitting Action Modification History
Modifications on 02/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| NOI to apply for an Air Permit submitted (Applicant Action) | 08-27-2027 | 08-27-2027 | --- | No |
| OCS Air Permit application submitted (Applicant Action) | 12-15-2027 | 12-15-2027 | --- | No |
| OCS Air Permit application complete (Applicant Action) | 09-15-2028 | 09-15-2028 | --- | No |
| Issuance of final decision/permit approval (Agency Action) | 09-17-2029 | 09-17-2029 | --- | No |