Permitting Action Modification History
Modifications on 05/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-23-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 04-10-2026 | 05-01-2026 | Yes |
Modifications on 04/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-23-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 04-10-2026 | 05-01-2026 | No |
Modifications on 02/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-23-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 04-10-2026 | --- | No |
Modifications on 01/26/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-23-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 03-27-2026 | --- | No |
Modifications on 01/09/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-26-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 03-27-2026 | --- | No |
Modifications on 09/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-09-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 03-27-2026 | --- | No |
Modifications on 09/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 01-09-2026 | 01-09-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 03-27-2026 | 03-27-2026 | --- | No |