Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-27-2025 06-27-2025 Yes
Issuance of a Final EA (Agency Action) 04-08-2026 04-08-2026 No
EA Process Concluded (Agency Action) 05-07-2026 05-07-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) --- 06-27-2025 Yes
Issuance of a Final EA (Agency Action) --- 04-08-2026 No
EA Process Concluded (Agency Action) --- 05-07-2026 No