USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Milestone data change due to FWS concluding consultation ahead of schedule , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 11-13-2025 Yes
ESA Consultation Concludes (Agency Action) 01-23-2026 11-13-2025 Yes
Planned
Milestone modification required due to a lapse in appropriation and furlough of USFWS staff , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 12-21-2025 No
ESA Consultation Concludes (Agency Action) 01-23-2026 04-06-2026 No
Planned
The scheduled revisions are due to the potential effects from the lapse in federal appropriations and to align the schedule with office calendars. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 11-21-2025 No
ESA Consultation Concludes (Agency Action) 01-23-2026 04-06-2026 No
Planned
The USFWS requested additional information to complete the ESA consultation package. The Corps sent the applicant a request for information to complete the ESA consultation package on September 16, 2025. To date, the Corps has not received additional information nor a timeline from the applicant on their response. The Corps is modifying the permitting timetable after coordination with the cooperating agency and the applicant to allow more time for the applicant to provide necessary information to complete the consultation package. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 10-14-2025 No
ESA Consultation Concludes (Agency Action) 01-23-2026 02-26-2026 No
Planned
The USFWS requested additional information to complete the ESA consultation package. The Corps sent the applicant a request for information to complete the ESA consultation package on September 16, 2025. To date, the Corps has not received additional information nor a timeline from the applicant on their response. The Corps is modifying the permitting timetable after coordination with the cooperating agency and the applicant to allow more time for the applicant to provide necessary information to complete the consultation package. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 10-14-2025 No
ESA Consultation Concludes (Agency Action) 01-23-2026 02-06-2026 No
Planned
USFWS needs more time for the completeness determination.  The Regulatory Project Manager has coordinated these milestone date changes with the agency and the sponsor.   , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-11-2025 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-10-2025 09-24-2025 No
ESA Consultation Concludes (Agency Action) 01-23-2026 02-06-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 08-11-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 09-10-2025 No
ESA Consultation Concludes (Agency Action) --- 01-23-2026 No