Permitting Action Modification History
Modifications on 11/14/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 11-13-2025 | Yes |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 11-13-2025 | Yes |
Modifications on 11/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 12-21-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 04-06-2026 | No |
Modifications on 10/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 11-21-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 04-06-2026 | No |
Modifications on 09/24/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 10-14-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 02-26-2026 | No |
Modifications on 09/24/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 10-14-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 02-06-2026 | No |
Modifications on 09/10/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-11-2025 | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-10-2025 | 09-24-2025 | No |
| ESA Consultation Concludes (Agency Action) | 01-23-2026 | 02-06-2026 | No |
Modifications on 09/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | --- | 08-11-2025 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | --- | 09-10-2025 | No |
| ESA Consultation Concludes (Agency Action) | --- | 01-23-2026 | No |