Permitting Action Modification History

Complete
Agency completed early , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 12-17-2025 Yes
ESA Consultation Concludes (Agency Action) 01-28-2026 03-19-2026 Yes
In Progress
Milestone date revised because FWS determined consultation request complete early. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 12-17-2025 Yes
ESA Consultation Concludes (Agency Action) 01-28-2026 04-06-2026 No
Planned
Milestone modification required due to a lapse in appropriation and furlough of USFWS staff , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 12-21-2025 No
ESA Consultation Concludes (Agency Action) 01-28-2026 04-06-2026 No
Planned
The scheduled revisions are due to the potential effects from the lapse in federal appropriations and to align the schedule with office calendars. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 11-21-2025 No
ESA Consultation Concludes (Agency Action) 01-28-2026 04-06-2026 No
Planned
The Corps initiated consultation with the USFWS on July 16, 2025. The USFWS requested additional information to complete the ESA consultation package. The Corps received the requested information from the applicant and sent it to the USFWS on September 19, 2025. The Corps provided some additional information about the consultation request on September 26, 2025. The Corps is modifying the permitting timetable after coordination with the cooperating agency and the applicant to allow more time for the USFWS to review the consultation request and determine completeness. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 10-14-2025 No
ESA Consultation Concludes (Agency Action) 01-28-2026 02-26-2026 No
Planned
The Corps initiated consultation with the USFWS on July 16, 2025. The USFWS requested additional information to complete the ESA consultation package. The Corps sent the applicant a request for information to complete the ESA consultation package on July 21, 2025. To date, the Corps has not received the additional information. The Corps is modifying the permitting timetable after coordination with the cooperating agency and the applicant to allow more time for the applicant to provide necessary information to complete the consultation package.   , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-16-2025 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-15-2025 09-29-2025 No
ESA Consultation Concludes (Agency Action) 01-28-2026 02-11-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 07-16-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 09-15-2025 No
ESA Consultation Concludes (Agency Action) --- 01-28-2026 No