Permitting Action Modification History
Modifications on 04/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 01-02-2025 | 01-02-2025 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 04-15-2025 | 04-15-2025 | Yes |
| Publication of Public Notice (Agency Action) | 05-13-2025 | 05-13-2025 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-12-2026 | 04-03-2026 | Yes |
Modifications on 09/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | --- | 01-02-2025 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | --- | 04-15-2025 | Yes |
| Publication of Public Notice (Agency Action) | --- | 05-13-2025 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | --- | 05-12-2026 | No |