Permitting Action Modification History

In Progress
The applicant provided a complete application on 9-3-26, before the 10-2-26 current target date., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 06-15-2026 06-15-2026 --- Yes
Completed application received (Applicant Action) 08-14-2026 09-03-2026 --- Yes
Issuance of decision for permit/approval (Agency Action 02-12-2027 02-12-2027 --- No
In Progress
Project Sponsor is working to supply a complete application with updated drawings to avoid wetlands on WMA, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 06-15-2026 06-15-2026 --- Yes
Completed application received (Applicant Action) 08-14-2026 10-02-2026 --- No
Issuance of decision for permit/approval (Agency Action 02-12-2027 02-12-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 06-15-2026 06-15-2026 --- Yes
Completed application received (Applicant Action) 08-14-2026 08-14-2026 --- No
Issuance of decision for permit/approval (Agency Action 02-12-2027 02-12-2027 --- No
Planned
USACE was deemed lead federal agency., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 06-15-2026 06-15-2026 --- No
Completed application received (Applicant Action) 08-14-2026 08-14-2026 --- No
Issuance of decision for permit/approval (Agency Action 02-12-2027 02-12-2027 --- No