Permitting Action Modification History

In Progress
Section 106 consultation initiation was completed 8/28/26; both hard copies and electronic copies have been sent to the consulting parties. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-28-2026 08-28-2026 --- Yes
Section 106 consultation concluded (Agency Action) 11-26-2026 11-26-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-28-2026 08-28-2026 --- No
Section 106 consultation concluded (Agency Action) 11-26-2026 11-26-2026 --- No