Permitting Action Modification History

In Progress
The National Park Service has reviewed the application materials submitted for the WSRA determination and deemed the application complete., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2026 07-23-2026 --- Yes
Application deemed complete (Agency Action) 08-08-2026 08-08-2026 07-29-2026 Yes
Final decision/agency action (Agency Action) 12-21-2026 12-21-2026 --- No
Planned
Internal coordination among USACE 408 and Regulatory, as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the action area.  This delay resulted in the 7/8/26 milestone shifting to 7/24/26 due to the domino effect to subsequent milestones.  Internal agency coordination completed a day earlier than anticipated allowing the milestone to be met on 7/23/2026., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2026 07-23-2026 --- Yes
Application deemed complete (Agency Action) 08-08-2026 08-08-2026 08-24-2026 No
Final decision/agency action (Agency Action) 12-21-2026 12-21-2026 --- No
Planned
Internal coordination among USACE 408 and Regulatory, as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the action area.  This delay resulted in a domino effect to subsequent milestones.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2026 07-24-2026 --- No
Application deemed complete (Agency Action) 08-08-2026 08-08-2026 08-24-2026 No
Final decision/agency action (Agency Action) 12-21-2026 12-21-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-08-2026 07-08-2026 --- No
Application deemed complete (Agency Action) 08-08-2026 08-08-2026 --- No
Final decision/agency action (Agency Action) 12-21-2026 12-21-2026 --- No