Permitting Action Modification History
Modifications on 03/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 10-16-2026 | 06-04-2027 | No |
| Scoping (Agency Action) | 11-15-2026 | 07-05-2027 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 09-10-2027 | 02-04-2028 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-15-2027 | 02-04-2028 | No |
Modifications on 10/23/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 10-16-2026 | 10-16-2026 | No |
| Scoping (Agency Action) | 11-15-2026 | 11-15-2026 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 09-10-2027 | 09-10-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-15-2027 | 10-15-2027 | No |