Permitting Action Modification History
Modifications on 10/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-15-2024 | 04-15-2024 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-15-2026 | 09-15-2026 | 11-16-2026 | No |
Modifications on 09/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-15-2024 | 04-15-2024 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-15-2026 | 09-15-2026 | 10-15-2026 | No |
Modifications on 10/14/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-15-2024 | 04-15-2024 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-15-2026 | 09-15-2026 | --- | No |
Modifications on 08/15/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-15-2024 | 04-15-2024 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-15-2026 | 07-15-2026 | --- | No |