Permitting Action Modification History

In Progress
California State Historic Preservation Officer (SHPO) raised procedural and documentation concerns, noting specifically that the VAA evaluated only the utility right-of-way and omitted the mine site area. SWCA had assumed the mine area was adequately covered under the general EIS analysis, failing to account for the distinct procedural requirements separating NEPA and Section 106. In response, the BLM directed SWCA to expand the VAA to include the mine site and resolve key eligibility determination gaps., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-13-2025 06-13-2025 --- Yes
Section 106 consultation concluded (Agency Action) 08-28-2026 02-26-2027 --- No
In Progress
The BLM CA Needles Field Office requested an Executive Director Determination to shift of the final Section 106 milestone to address to unresolved eligibility issues. The California and Nevada SHPOs formally disagreed with BLM’s determination that a pre-contact site is not eligible for the National Register and has advised that BLM engage in further consultation with Tribes before making any final eligibility determination. The extension was granted on July 27, 2026. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-13-2025 06-13-2025 --- Yes
Section 106 consultation concluded (Agency Action) 08-28-2026 11-13-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-13-2025 06-13-2025 --- Yes
Section 106 consultation concluded (Agency Action) 08-28-2026 08-28-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-13-2025 06-13-2025 --- No
Section 106 consultation concluded (Agency Action) 08-28-2026 08-28-2026 --- No