Permitting Action Modification History
Modifications on 10/09/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 01-16-2025 | 01-16-2025 | --- | Yes |
| Completed application received (Agency Action) | 04-04-2025 | 04-04-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-14-2026 | 03-30-2027 | --- | No |
Modifications on 07/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 01-16-2025 | 01-16-2025 | --- | Yes |
| Completed application received (Agency Action) | 04-04-2025 | 04-04-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-14-2026 | 01-29-2027 | --- | No |
Modifications on 08/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 01-16-2025 | 01-16-2025 | --- | Yes |
| Completed application received (Agency Action) | 04-04-2025 | 04-04-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-14-2026 | 12-14-2026 | --- | No |