Permitting Action Modification History
Modifications on 10/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 09-30-2026 | 09-30-2026 | 11-02-2026 | No |
Modifications on 05/19/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | Yes |
Modifications on 04/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-30-2026 | 09-30-2026 | --- | No |
Modifications on 04/18/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-30-2026 | 09-30-2026 | --- | No |
Modifications on 08/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-30-2026 | 09-30-2026 | --- | No |
Modifications on 08/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 04-17-2026 | 04-17-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 05-18-2026 | 05-18-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 09-30-2026 | 09-30-2026 | --- | No |