Permitting Action Modification History

In Progress
7/28/26 UPDATE: An approved jurisdictional determination was made on 7/22/2026. Through review of the original EA process, USACE initiated the determination that the Graphite Creek Project is likely to result in reasonably foreseeable significant effects and that preparation of an EIS is required due to the likely significant effects of the activity. Therefore, the EA action was cancelled and an EIS action was added to the dashboard. In addition, the Section 404 final permit decision milestone was modified to comport with the EIS evaluation., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-15-2025 08-15-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2025 09-15-2025 --- Yes
Publication of Public Notice (Agency Action) 09-30-2025 09-30-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-29-2026 09-24-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-15-2025 08-15-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2025 09-15-2025 --- Yes
Publication of Public Notice (Agency Action) 09-30-2025 09-30-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-29-2026 09-29-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-15-2025 08-15-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2025 09-15-2025 --- Yes
Publication of Public Notice (Agency Action) 09-30-2025 09-30-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-29-2026 09-29-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-15-2025 08-15-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2025 09-15-2025 --- No
Publication of Public Notice (Agency Action) 09-30-2025 09-30-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-29-2026 09-29-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-15-2025 08-15-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2025 09-15-2025 --- No
Publication of Public Notice (Agency Action) 09-30-2025 09-30-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-29-2026 09-29-2026 --- No