Permitting Action Modification History
Modifications on 08/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 07-18-2023 | 07-18-2023 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 05-18-2027 | 06-01-2028 | --- | No |
Modifications on 01/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 07-18-2023 | 07-18-2023 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 05-18-2027 | 06-01-2028 | --- | No |
Modifications on 07/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 07-18-2023 | 07-18-2023 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 05-18-2027 | 05-18-2027 | --- | No |