Permitting Action Modification History
Modifications on 10/02/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 10-01-2025 | 10-01-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 03-26-2027 | 03-26-2027 | --- | No |
| Final decision/agency action (Agency Action) | 05-25-2027 | 05-25-2027 | --- | No |
Modifications on 07/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 10-01-2025 | 10-01-2025 | --- | No |
| Application deemed complete (Agency Action) | 03-26-2027 | 03-26-2027 | --- | No |
| Final decision/agency action (Agency Action) | 05-25-2027 | 05-25-2027 | --- | No |
Modifications on 07/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 10-01-2025 | 10-01-2025 | --- | No |
| Application deemed complete (Agency Action) | 03-26-2027 | 03-26-2027 | --- | No |
| Final decision/agency action (Agency Action) | 05-25-2027 | 05-25-2027 | --- | No |