Permitting Action Modification History
Modifications on 08/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 04-03-2026 | 11-12-2026 | --- | No |
| Scoping (Agency Action) | 04-03-2026 | 11-12-2026 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-02-2026 | 09-07-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-18-2027 | 07-03-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 11-17-2027 | 11-17-2028 | --- | No |
Modifications on 01/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 04-03-2026 | 11-12-2026 | --- | No |
| Scoping (Agency Action) | 04-03-2026 | 11-12-2026 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-02-2026 | 09-07-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-18-2027 | 07-03-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 11-17-2027 | 11-17-2028 | --- | No |
Modifications on 07/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 04-03-2026 | 04-03-2026 | --- | No |
| Scoping (Agency Action) | 04-03-2026 | 04-03-2026 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-02-2026 | 12-02-2026 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-18-2027 | 06-18-2027 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 11-17-2027 | 11-17-2027 | --- | No |