USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
Milestone completed one day early , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-27-2026 02-26-2026 --- Yes
Issuance of a Final EA (Agency Action) 02-26-2027 02-26-2027 --- No
EA Process Concluded (Agency Action) 03-26-2027 03-26-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-27-2026 02-27-2026 --- No
Issuance of a Final EA (Agency Action) 02-26-2027 02-26-2027 --- No
EA Process Concluded (Agency Action) 03-26-2027 03-26-2027 --- No