Permitting Action Modification History

In Progress
Milestone completed one day early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2025 01-25-2025 --- Yes
Request for additional information (Agency Action) 04-10-2025 04-10-2025 --- Yes
Additional information submitted (Applicant Action) 12-31-2025 12-15-2025 --- Yes
Acceptance review complete (Agency Action) 02-27-2026 02-26-2026 --- Yes
Issuance of licensing decision (Agency Action) 03-26-2027 03-26-2027 --- No
Planned
Early completion of the milestone on Dec 15 by the project sponsor, in advance of the Dec 31 original target date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2025 01-25-2025 --- Yes
Request for additional information (Agency Action) 04-10-2025 04-10-2025 --- Yes
Additional information submitted (Applicant Action) 12-31-2025 12-15-2025 --- Yes
Acceptance review complete (Agency Action) 02-27-2026 02-27-2026 --- No
Issuance of licensing decision (Agency Action) 03-26-2027 03-26-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2025 01-25-2025 --- Yes
Request for additional information (Agency Action) 04-10-2025 04-10-2025 --- Yes
Additional information submitted (Applicant Action) 12-31-2025 12-31-2025 --- No
Acceptance review complete (Agency Action) 02-27-2026 02-27-2026 --- No
Issuance of licensing decision (Agency Action) 03-26-2027 03-26-2027 --- No