Permitting Action Modification History
Modifications on 10/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-27-2027 | 06-30-2028 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-27-2027 | 07-28-2028 | --- | No |
| ESA Consultation Concludes (Agency Action) | 02-11-2028 | 11-09-2028 | --- | No |
Modifications on 07/11/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-27-2027 | 09-27-2027 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-27-2027 | 10-27-2027 | --- | No |
| ESA Consultation Concludes (Agency Action) | 02-11-2028 | 02-11-2028 | --- | No |