Permitting Action Modification History

Planned
NRC’s review of the uranium recovery license application depends on a thorough characterization of baseline hydrologic conditions at the Project site, which includes groundwater testing. NMED requires the Project Sponsor to hold a discharge permit to conduct that testing which is necessary to collect the data needed to submit a complete NRC uranium recovery license application. The Project Sponsor’s initial schedule to prepare its NRC application accounted for the time needed to collect hydrologic data but not for the foregoing state permitting process., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-26-2027 10-26-2027 --- No
Section 106 consultation concluded (Agency Action) 04-19-2028 01-26-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-26-2027 01-26-2027 --- No
Section 106 consultation concluded (Agency Action) 04-19-2028 04-19-2028 --- No