Permitting Action Modification History

Planned
NRC’s review of the uranium recovery license application depends on a thorough characterization of baseline hydrologic conditions at the Project site, which includes groundwater testing. NMED requires the Project Sponsor to hold a discharge permit to conduct that testing which is necessary to collect the data needed to submit a complete NRC uranium recovery license application. The Project Sponsor’s initial schedule to prepare its NRC application accounted for the time needed to collect hydrologic data but not for the foregoing state permitting process., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-30-2026 06-30-2027 --- No
Acceptance review complete (Agency Action) 11-27-2026 08-27-2027 --- No
Issuance of licensing decision (Agency Action) 05-26-2028 02-27-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-30-2026 09-30-2026 --- No
Acceptance review complete (Agency Action) 11-27-2026 11-27-2026 --- No
Issuance of licensing decision (Agency Action) 05-26-2028 05-26-2028 --- No