USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
On October 16, 2026, submissions of the Biological, Cultural, and Geochemistry baseline reports for the Golden Mile Mine Project were received. BLM and NDEP have identified a need for additional time to complete a thorough review of the Geochemistry report. The new target date to deem the application complete is 12/14/2026., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 11-27-2025 11-24-2025 Yes
Application deemed complete (Agency Action) 07-23-2026 12-14-2026 No
Final decision/agency action (Agency Action) 06-28-2027 04-30-2027 No
Planned
Company submitted the revised Mine Plan of Operations ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 11-27-2025 11-24-2025 Yes
Application deemed complete (Agency Action) 07-23-2026 10-31-2026 No
Final decision/agency action (Agency Action) 06-28-2027 04-30-2027 No
Planned
After further coordination with the project sponsor, the milestones were updated to better reflect the proposed target dates. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 11-27-2025 11-27-2025 No
Application deemed complete (Agency Action) 07-23-2026 10-31-2026 No
Final decision/agency action (Agency Action) 06-28-2027 04-30-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) --- 11-27-2025 No
Application deemed complete (Agency Action) --- 07-23-2026 No
Final decision/agency action (Agency Action) --- 06-28-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) --- 11-27-2025 No
Application deemed complete (Agency Action) --- 07-23-2026 No
Final decision/agency action (Agency Action) --- --- No