Permitting Action Modification History
Modifications on 10/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial application submitted (Applicant Action) | 11-27-2025 | 11-24-2025 | Yes |
| Application deemed complete (Agency Action) | 07-23-2026 | 12-14-2026 | No |
| Final decision/agency action (Agency Action) | 06-28-2027 | 04-30-2027 | No |
Modifications on 11/24/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial application submitted (Applicant Action) | 11-27-2025 | 11-24-2025 | Yes |
| Application deemed complete (Agency Action) | 07-23-2026 | 10-31-2026 | No |
| Final decision/agency action (Agency Action) | 06-28-2027 | 04-30-2027 | No |
Modifications on 08/08/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial application submitted (Applicant Action) | 11-27-2025 | 11-27-2025 | No |
| Application deemed complete (Agency Action) | 07-23-2026 | 10-31-2026 | No |
| Final decision/agency action (Agency Action) | 06-28-2027 | 04-30-2027 | No |
Modifications on 08/07/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial application submitted (Applicant Action) | --- | 11-27-2025 | No |
| Application deemed complete (Agency Action) | --- | 07-23-2026 | No |
| Final decision/agency action (Agency Action) | --- | 06-28-2027 | No |
Modifications on 07/10/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial application submitted (Applicant Action) | --- | 11-27-2025 | No |
| Application deemed complete (Agency Action) | --- | 07-23-2026 | No |
| Final decision/agency action (Agency Action) | --- | --- | No |