Permitting Action Modification History
Modifications on 07/01/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 02-29-2024 | 02-29-2024 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 03-22-2024 | 03-22-2024 | Yes |
| Publication of Public Notice (Agency Action) | 04-01-2024 | 04-01-2024 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 07-01-2025 | 07-01-2025 | Yes |
Modifications on 06/06/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | --- | 02-29-2024 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | --- | 03-22-2024 | Yes |
| Publication of Public Notice (Agency Action) | --- | 04-01-2024 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | --- | 07-01-2025 | No |