Permitting Action Modification History
Modifications on 09/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 11-15-2025 | 11-15-2025 | No |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 12-22-2025 | 12-22-2025 | No |
| ESA Consultation Concludes (Agency Action) | 02-01-2026 | 02-01-2026 | No |
Modifications on 05/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | --- | 11-15-2025 | No |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | --- | 12-22-2025 | No |
| ESA Consultation Concludes (Agency Action) | --- | 02-01-2026 | No |