Permitting Action Modification History

Complete
Completed on 1/29/2026 due to internal delays. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2024 03-18-2024 Yes
Scoping (Agency Action) 04-17-2024 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-12-2025 08-08-2025 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-18-2026 01-29-2026 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2026 01-29-2026 Yes
In Progress
BLM needed additional time to complete the FEIS and ROD. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2024 03-18-2024 Yes
Scoping (Agency Action) 04-17-2024 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-12-2025 08-08-2025 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-18-2026 01-23-2026 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2026 01-23-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2024 03-18-2024 Yes
Scoping (Agency Action) 04-17-2024 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-12-2025 08-08-2025 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-18-2026 12-19-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2026 12-19-2025 No
In Progress
The proponent has requested the most accurate dates from our ongoing NEPA analysis be posted on the dashboard , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2024 03-18-2024 Yes
Scoping (Agency Action) 04-17-2024 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-12-2025 08-08-2025 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-18-2026 12-19-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2026 12-19-2025 No
In Progress
The work on these milestones is ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2024 03-18-2024 Yes
Scoping (Agency Action) 04-17-2024 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-12-2025 08-01-2025 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-18-2026 12-15-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-01-2026 12-15-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) --- 03-18-2024 Yes
Scoping (Agency Action) --- 04-17-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) --- 08-12-2025 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) --- 03-18-2026 No
Issuance of Lead Agency Record of Decision (Agency Action) --- 05-01-2026 No