Modifications on 07/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-17-2026 | 06-15-2026 | Yes |
| Scoping (Agency Action) | 02-17-2026 | 06-16-2026 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-11-2026 | 06-25-2027 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 05-28-2027 | 01-14-2028 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-31-2025 | 04-25-2028 | No |
Modifications on 06/15/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-17-2026 | 06-15-2026 | Yes |
| Scoping (Agency Action) | 02-17-2026 | 07-15-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-11-2026 | 06-25-2027 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 05-28-2027 | 01-14-2028 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-31-2025 | 04-25-2028 | No |
Modifications on 05/08/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-17-2026 | 06-15-2026 | No |
| Scoping (Agency Action) | 02-17-2026 | 07-15-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-11-2026 | 06-25-2027 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 05-28-2027 | 01-14-2028 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-31-2025 | 04-25-2028 | No |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-17-2026 | 05-18-2026 | No |
| Scoping (Agency Action) | 02-17-2026 | 05-19-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-11-2026 | 12-11-2026 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 05-28-2027 | 05-28-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-31-2025 | 10-31-2027 | No |
Modifications on 06/06/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-17-2026 | 02-17-2026 | No |
| Scoping (Agency Action) | 02-17-2026 | 02-17-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-11-2026 | 12-11-2026 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 05-28-2027 | 05-28-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-31-2025 | 10-31-2027 | No |
Modifications on 05/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 02-17-2026 | No |
| Scoping (Agency Action) | --- | 02-17-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 12-11-2026 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 05-28-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 10-31-2025 | No |