Permitting Action Modification History
Modifications on 08/12/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 11-09-2023 | 11-09-2023 | Yes |
| Section 106 consultation concluded (Agency Action) | 07-01-2025 | 11-09-2023 | Yes |
Modifications on 05/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 11-09-2023 | 11-09-2023 | Yes |
| Section 106 consultation concluded (Agency Action) | 07-01-2025 | 07-01-2025 | No |