Modifications on 06/11/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 04-14-2025 | 04-14-2025 | Yes |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 05-12-2025 | 05-12-2025 | Yes |
| Issuance of a Final EA (Agency Action) | 06-02-2025 | 06-05-2025 | Yes |
| EA Process Concluded (Agency Action) | 06-02-2025 | 06-05-2025 | Yes |
Modifications on 05/15/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | --- | 04-14-2025 | Yes |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | --- | 05-12-2025 | Yes |
| Issuance of a Final EA (Agency Action) | --- | 06-02-2025 | No |
| EA Process Concluded (Agency Action) | --- | 06-02-2025 | No |