Permitting Action Modification History

Cancelled
The ACHP informed the Forest Service in a November 19, 2025 meeting that they considered consultation closed on the previous project.  A new Section 106 consultation file will be started on the new Proposed Action. The agency is cancelling this action and entering a new one to show the new start date. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-01-2013 01-01-2013 Yes
Section 106 consultation concluded (Agency Action) 05-14-2027 05-14-2027 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-01-2013 01-01-2013 Yes
Section 106 consultation concluded (Agency Action) 05-14-2027 05-14-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) --- 01-01-2013 No
Section 106 consultation concluded (Agency Action) --- 05-14-2027 No