Permitting Action Modification History
Modifications on 08/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 03-31-2027 | 03-31-2027 | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 04-01-2027 | 04-01-2027 | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 07-29-2027 | 07-29-2027 | No |
Modifications on 05/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | --- | 03-31-2027 | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | --- | 04-01-2027 | No |
| Final Verification/Permit Decision Rendered (Agency Action) | --- | 07-29-2027 | No |