Permitting Action Modification History

Complete
Ahead of Schedule , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-28-2025 02-28-2025 Yes
Issuance of a Final EA (Agency Action) 06-09-2025 06-05-2025 Yes
EA Process Concluded (Agency Action) 06-09-2025 06-05-2025 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) --- 02-28-2025 Yes
Issuance of a Final EA (Agency Action) --- 06-09-2025 No
EA Process Concluded (Agency Action) --- 06-09-2025 No