Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Aquifer exemption request submitted (Applicant Action) 06-18-2024 06-18-2024 Yes
Aquifer exemption decision (Agency Action) 06-29-2026 10-24-2025 Yes
In Progress
There has been coordination between the BLM and EPA on a change of approach for this EIS, which resulted in an earlier milestone decision date. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Aquifer exemption request submitted (Applicant Action) 06-18-2024 06-18-2024 Yes
Aquifer exemption decision (Agency Action) 06-29-2026 10-24-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Aquifer exemption request submitted (Applicant Action) 06-18-2024 06-18-2024 Yes
Aquifer exemption decision (Agency Action) 06-29-2026 06-29-2026 No